Project name:
PJSC "Philip Morris Ukraine"
Project date:
January 2020
TASK:
In this project, the task was set to modernize the lighting system of the production facility "Cigarette Filter Production Shop".
decision:
In this project, it was decided to replace the existing energy-intensive luminaires with MGL-250W lamps with new LED-SVU-I-C-04-141 (75W) luminaires in the Cobay housing - in the amount of 20 pcs.
before | after |
МГЛ-250 Вт | LED-SVU-I-C-04-141(75Вт) |
![]() |
THE RESULT OF CONDUCTED MODERNIZATION:
characteristics | before | after |
Consumed power, W | 300 | 75 |
Consumed electric power, kW/h | 55 | 16,5 |
Illumination on working surface, Lx | 36 | 300 |
As a result of the modernization, the data in the table show that the energy consumption decreased by 75%, while the level of illumination increased several times.
other projects

Kostopil plant
February, 2016
Kremenchug Wheel Plant
May, 2015
Odeskabel
August, 2014
Nowy Styl
January, 2015
RosanPak
December, 2015
AB InBev Efes Ukraine "HO Pizavod R..
December, 2013
AB InBev Efes Ukraine "HO Pizavod R..
December, 2014
TNK petrol station
September, 2013-January, 2016
TATNEFT Petrol station
April, 2013-July, 2014
Petrol station MARSHAL
December, 2012-May, 2013
WOG petrol station
December, 2012-May, 2016
CATRAL petrol station
Juni-August, 2013
Livarny plant
October, 2015-May, 2016
Most-city сentre
March, 2016
PJSC Zaporozhkran
December, 2019
Odessa Sea Commercial Port. Author's sup..
2019 - 2020
LLC "GLUSKO RETAIL" gas statio..
January, 2020
MP "Contact" Mirgorod
September, 2019
LLC "SIGMA UKRAINE"
September 2018
PJSC "Philip Morris Ukraine"
January 2020
Gas station №2102 Brand: "GLUSCO&qu..
July 2019
Object IC "Illichivets" (open..
October 2019
PJSC '' Plemzavod Stepnoy ''
July 2019
LLC "D LIGHT"
August 2019
ODO "NOVOIVANOVSKY SUGAR FACTORY&qu..
August 2019
PJSC "Krukovka Carriage Works"
September 2019
BUDMAN
2019-2020
PJSC '' Plemzavod Stepnoy ''
November 2019
MAGMA LLC
July 2019