Project name:

Facility SC "Illichivets" (open training field №2) Customer: LLC "Elektromontazhservis"

Project date:

December 2020

TASK:

Provide uniform illumination at every point of the training field and structures (masts) on it. The main problem was the inaccessibility of the field due to nearby communications and the slope, which was 2.5m of uneven surface and 13.5m distance from the field at the upper left point.

decision:

In this project, it was decided to illuminate the training field with LED-SVU-PW-09-K20(400W) GRAND MAX floodlights in the amount of 40 pcs, LED-SVU-PW-06-K10(240W) GRAND MAX in the amount of 4 pcs and LED- SVU-PW-03-K10(120W) GRAND MAX, 4 pcs.

Mounted LED Downlight
LED-SVU-P-W-06-К10(240W) GRAND MAX LED-SVU-P-W-09-K20(400W) GRAND MAXLED-SVU-P-W-03-К10(120W) GRAND MAX

THE RESULT OF CONDUCTED MODERNIZATION:

characteristics

LED-SVU-P-W-06-К10(240W) GRAND MAXLED-SVU-P-W-09-K20(400W) GRAND MAXLED-SVU-P-W-03-К10(120W) GRAND MAX

Consumed power, W

 

240
400120

Consumed electric power, kW/h

115,2
19257,6

Illumination on working surface, Lx

 

200

As a result of the modernization, electricity consumption decreased, while the level of illumination increased several times.